Question | Strongly disagree | Disagree | Slightly disagree | Slightly agree | Agree | Strongly agree | No opinion | Mean |
1.01 I believe Project XXX has sufficient business input – our hands are all over it [12] | 0 | 2 | 1 | 3 | 5 | 1 | 0 | 63.33% |
1.02 Our business leaders support Project XXX and want it to happen [12] | 0 | 2 | 0 | 4 | 3 | 3 | 0 | 68.33% |
1.03 My Line Supervisor demonstrates visible commitment to Project XXX [12] | 0 | 3 | 1 | 2 | 5 | 1 | 0 | 60% |
GroupMean =63.89% |
Question | Strongly disagree | Disagree | Slightly disagree | Slightly agree | Agree | Strongly agree | No opinion | Mean |
2.01 There is a real sense of urgency in the broader business to implement Project XXX [12] | 0 | 1 | 0 | 1 | 4 | 6 | 0 | 83.33% |
2.02 There is a real sense of urgency at my site to implement Project XXX [12] | 0 | 1 | 2 | 2 | 3 | 4 | 0 | 71.67% |
2.03 There is a real sense of urgency for me personally to implement Project XXX [12] | 0 | 3 | 4 | 0 | 3 | 2 | 0 | 55% |
GroupMean =70% |
Question | Strongly disagree | Disagree | Slightly disagree | Slightly agree | Agree | Strongly agree | No opinion | Mean |
3.01 I understand Project XXX objectives and intent [12] | 0 | 3 | 1 | 3 | 2 | 3 | 0 | 61.67% |
3.02 I agree with Project XXX objectives and intent [12] | 0 | 3 | 4 | 1 | 3 | 1 | 0 | 51.67% |
3.03 I believe that Project XXX will help us achieve our business goals [12] | 0 | 2 | 1 | 6 | 1 | 2 | 0 | 60% |
3.04 I believe that Project XXX will help me achieve my personal goals [12] | 0 | 1 | 2 | 3 | 3 | 3 | 0 | 68.33% |
GroupMean =60.42% |
Question | Strongly disagree | Disagree | Slightly disagree | Slightly agree | Agree | Strongly agree | No opinion | Mean |
4.01 I am, or have been, sufficiently consulted on Project XXX requirements [12] | 0 | 2 | 3 | 4 | 1 | 2 | 0 | 56.67% |
4.02 I believe that the Project Team have taken my views and inputs into account in their deliberations [12] | 0 | 2 | 3 | 1 | 5 | 1 | 0 | 60% |
4.03 I am sufficiently informed on Project XXX activities and progress [12] | 0 | 3 | 1 | 3 | 5 | 0 | 0 | 56.67% |
GroupMean =57.78% |
Question | Strongly disagree | Disagree | Slightly disagree | Slightly agree | Agree | Strongly agree | No opinion | Mean |
5.01 I know who is my Project XXX business representative [12] | 0 | 2 | 1 | 2 | 5 | 2 | 0 | 66.67% |
5.02 Relationships between the Project XXX team and my business are open & effective [12] | 0 | 3 | 2 | 3 | 3 | 1 | 0 | 55% |
5.03 I believe the Project XXX team will ensure that the project is well supported [12] | 0 | 3 | 1 | 3 | 4 | 1 | 0 | 58.33% |
5.04 I am prepared to support recommendations of the Project XXX team [12] | 0 | 1 | 3 | 3 | 3 | 2 | 0 | 63.33% |
GroupMean =60.83% |
Question | Strongly disagree | Disagree | Slightly disagree | Slightly agree | Agree | Strongly agree | No opinion | Mean |
6.01 There is a clear plan/roadmap to complete Project XXX [12] | 0 | 2 | 3 | 4 | 2 | 1 | 0 | 55% |
6.02 I believe the plan/roadmap is right for our business [12] | 0 | 2 | 3 | 2 | 2 | 3 | 0 | 61.67% |
6.03 The Project XXX Team are delivering on this plan/roadmap [12] | 0 | 3 | 4 | 0 | 2 | 3 | 0 | 56.67% |
GroupMean =57.78% |
Question | Strongly disagree | Disagree | Slightly disagree | Slightly agree | Agree | Strongly agree | No opinion | Mean |
7.01 Project XXX has good momentum and buy in within our business [12] | 0 | 3 | 3 | 4 | 2 | 0 | 0 | 48.33% |
7.02 Project XXX has delivered quick hit benefits for our business [12] | 0 | 0 | 4 | 3 | 3 | 2 | 0 | 65% |
7.03 Project XXX benefits are well publicized [12] | 0 | 4 | 2 | 3 | 2 | 1 | 0 | 50% |
7.04 Project XXX supports our work processes - how we do our work [12] | 0 | 0 | 1 | 4 | 6 | 1 | 0 | 71.67% |
7.05 I am confident that Project XXX will endure in our business [12] | 0 | 0 | 2 | 5 | 1 | 4 | 0 | 71.67% |
GroupMean =61.33% |
Question | Strongly disagree | Disagree | Slightly disagree | Slightly agree | Agree | Strongly agree | No opinion | Mean |
8.01 I believe that having common processes across our business is a good thing [12] | 0 | 3 | 2 | 3 | 3 | 1 | 0 | 55% |
8.02 I believe standard definitions across our business is a good thing [12] | 0 | 3 | 0 | 2 | 3 | 4 | 0 | 68.33% |
8.03 I believe that common calculation methodologies across our business is a good thing [12] | 0 | 3 | 1 | 4 | 3 | 1 | 0 | 56.67% |
8.04 I believe that Project XXX will provide me with adequate functionality and analytical capability [12] | 0 | 3 | 0 | 3 | 3 | 3 | 0 | 65% |
8.05 I believe that the adoption of common processes and systems will yield more ideas for improvement [12] | 0 | 3 | 1 | 2 | 3 | 3 | 0 | 63.33% |
8.06 I believe that current governance mechanisms will adequately cater for the requirements of the new system [12] | 0 | 2 | 1 | 2 | 4 | 3 | 0 | 68.33% |
GroupMean =62.78% |
9.1 The KEY BENEFITS that I am obtaining from Project XXX are : | 12 Responses |